Load Assessment
We calculate your current electrical load and the load of all new equipment being added. This determines whether a simple capacity upgrade handles the need or whether a full service upgrade including an Oncor transformer upgrade is required.
Oncor Coordination
Commercial service upgrades that require increased amperage from the utility involve Oncor. We coordinate the Oncor application, confirm transformer capacity at your location, and schedule the Oncor meter pull. Oncor lead times for commercial service work can run two to six weeks — we factor this into the project timeline upfront.
Permit and Inspection
City of Arlington commercial electrical permits are required for panel upgrades. We pull the permit before starting, schedule the rough-in inspection, and handle the final inspection. We do not hand you a completed job without a passing inspection.